Construction Continues and RFID is Coming!

Phase 3 construction continues at the Main Library, and great progress is being made on the new Children’s Library, which is expected to open in mid-October. Other exciting changes are coming soon. Beginning Sept. 29, the outside materials return (pictured … Continue reading

Posted in Library News, Main Library Renovation | Comments Off

Renvation Update: Foundry Celebration, Work to Begin on New Children’s Area

Come one, come all! We are holding a grand opening celebration of The Foundry, the Main Library’s new tech lab, on the second floor adjacent to the Teen Space, from 4 to 6 p.m. on Thursday, Aug. 7. We hope … Continue reading

Posted in Library News, Main Library Renovation | Comments Off

Renovation Update: Come Check Out Some Fiction!

With construction in the Main Library’s second-floor Reference area winding down and expected to be complete by the end of this month, we are looking ahead to the Renovation’s third phase of construction. This phase will see the building of … Continue reading

Posted in Main Library Renovation | Comments Off

Renovation Update: Construction Phase 3 to Begin in August

Thanks to all of our patrons and supporters for your patience and enthusiasm during our ongoing renovation! Beginning in late July, Phase III begins. During this phase, the Main Library’s Fiction collection will be packed up as construction begins to … Continue reading

Posted in Main Library Renovation | Comments Off

Renovation Update: Construction Phase 1 Winds Down, Phase 2 Ramps Up

Phase 1 of the renovation is wrapping up next week, and Phase 2 is set to begin! Beginning middle to late next week (May 21-23), the 2nd floor adult non-fiction collection, study areas, and restrooms will reopen to the public … Continue reading

Posted in Library News, Main Library Renovation | Comments Off

Main Library Renovation: Second Floor News

The renovation of the BPL’s Main Library has moved into the last part of the plan for re-arranging and re-shelving the adult non-fiction collection on the second floor. Starting Monday, April 28, patrons will no longer be allowed back in the 2nd-floor area … Continue reading

Posted in Main Library Renovation | Comments Off

Main Library Renovation Update: Schedule Modified

Construction continues in the first phase of the Main Library renovation. The Request for Proposals (RFP) issued for cafe services on the bridge remains open until this Friday, April 4. Qualified vendors interested in submitting a proposal may contact the project … Continue reading

Posted in Main Library Renovation | Comments Off

Request for Proposals for café services at the Main Boulder Public Library

The City of Boulder has posted a Request for Proposals (RFP) for café services at the Main Boulder Public Library, on the bridge. Please see the full RFP for detailed information. Proposal responses to the RFP are due by April … Continue reading

Posted in Main Library Renovation | Comments Off

Main Library Renovation Update: The Bridge

Thanks again for your patience as our renovation construction rolls on! This week work began to renovate the bridge for café services. While this work is going on, the bridge will be closed off to all but staff and construction workers … Continue reading

Posted in Library News, Main Library Renovation | Comments Off

Main Library Renovation Update

The renovation of the Main Library has begun. We are beginning by building our new Teen Space on the second floor! Here is a timeline of this phase: Tuesday, February 18: The first third of the Adult Non-Fiction collection (Dewey … Continue reading